To solve the shortage of water supply capacity of an existing drinking water treatment plant (125,000 m³/day) caused by population increases, we installed flocculation tanks, sedimentation tanks, rapid filtration tanks, and chemical dosing facilities, which increased the water supply capacity to 250,000 m³/day.
Facility | Drinking water treatment plant |
---|---|
Capacity | 125,000m³/day |
Overview of water treatment plant
Flocculation tank
Sedimentation tank
Rapid filtration tank
Central monitoring room
To solve the shortage of water supply capacity of an existing drinking water treatment plant (35,000 m³/day) caused by population increases, we installed flocculation tanks, sedimentation tanks, rapid filtration tanks, and chlorine dosing facilities, which increased the water supply capacity to 70,000 m³/day.
Facility | Drinking water treatment plant |
---|---|
Capacity | 35,000m³/day |
Overview of water treatment plant
Rapid filtration tank
Sludge thickening tank
11kV receiving board
Low-voltage distribution board